This is an open forum in which Alpine Woods Area Residents can ask questions and respond to any and all information the City of Valdez posts. For downloadable documents, photos, and septic information please visit the official City of Valdez 10 - mile area website.

Thursday, August 13, 2009

A Rainy Week

Rockwell Engineering & Construction is in Valdez evaluating their sites & scheduling their construction. They will be doing some dewatering planning and some site clearing and preparation so that they will have multiple sites ready to go. The Orenco representative will be in Valdez August 24th to assist on the first Phase II AdvanTex install. This will give them a smooth path to move forward on.

King Bee Equipment's crew is still largely up in Blueberry Lake Campground assisting Harris Sand and Gravel. You may see them in the subdivision when the mound septic tanks get delivered. The remaining six will be insulated.

Option 2 mail outs went out to residents who were not in Phase I or Phase II. The City is still working on an Option 2 guide (and perhaps an Option1 guide as well) to pull all the information together into one booklet for residents. We will probably meet with the Oversight Group for their review and comment before releasing it to the public. The Oversight Group always provides good insight and can spot things the City misses in the daily bustle.

Don’t forget if you would like to move forward with Option 2 this construction season, contact the Community Development department right away. Those of you thinking about next season have until October 2nd, 2009.

The hydroseeded grass for Phase I sites has been happily soaking up the rain and growing like gang-busters. The Phase I sites have been transformed from rocky dirt fields to bright green lawns in the span of a few weeks. We are happy to report 17 out of the 18 systems have been completely finished. Take a look!




That’s all from City Hall. Keep an eye out from Rockwell Engineering and let the City know what’s going on out there. We’re always happy to hear from you.

Thursday, August 6, 2009

King Bee Temporary Work Suspension

King Bee Equipment has temporarily left the Alpine Woods Area because they are the subcontractor to Harris Sand & Gravel on the Blueberry Lake Campground paving project (this is a Stimulus fund project). King Bee has assured us, and our Site Engineer agrees, that they will have plenty of time to come back and finish their septic installations. They expect the delay to be approximately 2-3 weeks and will supply us with a revised installation schedule as soon as possible. The City of Valdez is still working with King Bee on the status of the two installations that have already been started. In the interim, King Bee is working on insulating the mound systems tanks and will be available to receive them once they are shipped from Anchorage.

We apologize to the Phase II mound systems residents for this delay to their septic installations. We were not aware that this interruption would be taking place until early this week. We look forward to King Bee’s return and the continuation of the mound installations.

Tuesday, August 4, 2009

Progress is Being Made

Good Morning Savvy Septic Readers! The City has lots of updates for you all today so let’s get to them:
Rockwell Engineering & Construction will be in Valdez at the end of this week. They will be coordinating site inspection for Group A and Group B of the AdvanTex installations with Dave Lanning. This is for their onsite crew to determine exact access, what (if anything) the homeowner needs to move, and whether they will have to have the electric and telephone companies move their utility lines. They expect their full crew to be here, starting their first AdvanTex installation in Valdez, around the 14th of August. This gives Phase II AdvanTex owners about 2 weeks to remove any private property that is in the way of access to the construction site or in the way of the construction site itself.

Due to the late start of the installs, it is unlikely that there will be time in the season to put finishing touches on any of the systems (Mound or AdvanTex) without a risk of wintertime and spring erosion. It is likely that the topsoil and hydro seeding will have to take place in the spring of next year (the way Phase I systems were handled) in order to ensure successful and strong growth in disturbed areas of properties. The systems will be fully operational and the only thing that will be affected by this delay will be the cosmetics of the yards.

It was brought to the City’s attention that mound tanks could also be insulated. Insulating mound system tanks is standard practice in Anchorage and, although the DEC does not require mound tanks to be insulated, the City decided to go ahead and insulate the remainder of the mound system tanks while they were still in Anchorage.

Last night on August 3rd, the Council approved the revisions and clarifications to Option 2 (homeowner installation) of the program. The City will be mailing out the new details to Alpine Woods Area residents who do not already have a new septic system (or for whom one isn’t planned for installation this year). The Option 2 details will also be available on the City website for reference (to see them now, click here).

There are just a few other things that have come up over the past week. The DEC went through the subdivision and did effluent testing for 16 of the AdvanTex systems. The city doesn’t have those results back yet but has heard by word of mouth that they looked good. Two systems had higher turbidity than the rest and this is likely because of improper things being poured down the drains into the septic systems. The EPA recommends that homeowners treat their septic systems like investments. The better they are treated the longer they last and the more value they add to the home. Pouring large amounts of grease and harsh chemical detergents into the system will harm the system and decrease its value and ability to last in the long run. For a general guide on how to take care of any septic system, click here.

Additionally, the City ran into some understandable confusion about tree felling and removal policies during Phase I and would like to clarify several points moving forward. The City will have its contractors fell the trees and it is up to the homeowner to either have the contractor drag the whole tree to an area agreed upon or to haul the whole tree off the property. If the homeowner wants to keep the tree for firewood and has the contractor put it somewhere they can work with it, it is no longer the contractor’s responsibility to deal with any part of the tree. After the homeowner bucks it up and takes whatever part of the tree they want for firewood, it is the homeowner’s responsibility to clear any remaining branches and mess. This was not made as clear as it should have been, but if the homeowner chooses to keep the tree for firewood they are responsible for all parts of the tree.

So, the Phase I systems are looking pretty green and healthy. The Phase II mound installs are moving forward steadily and the remaining six tanks will be insulated. And the Phase II AdvanTex systems (already insulated) will be starting up within two weeks. That feels like real progress! Let us know what you think about it too.